Feed-In / Export
The energy a PV system sends to the public grid when generation exceeds on-site demand. It is measured by a bidirectional meter and remunerated or netted according to the local regulatory scheme.
Export terms vary enormously by country and change over time, so a design assumption about their value should be treated as the least durable number in a financial model. What is technically fixed is the connection agreement: the network operator authorises a maximum export power, which is often lower than the inverter's rating and is enforced by curtailment settings in the inverter or an external meter. Where export is poorly paid or capped, the design logic shifts towards self-consumption and storage rather than towards maximising annual generation.